The Florida Department of Transportation has proposed design improvements to the intersection of Gunn Highway & Linebaugh Avenue include changes that are needed to reduce vehicle delay, improve safety, and reduce accident occurrences. The project cost is estimated to be $1.5 million. The design improvements include:

  • removal of the westbound left turn lane
  • addition of a westbound right turn lane
  • addition of a northbound left turn lane
  • addition of an eastbound right turn lane
  • extending the existing southbound left turn lane

For more information, view the Hillsborough TIP tool or contact Joe Price at pricej@plancom.org or 813/273-3774 x362.